Duration Uncertainty Tab of the Activity Details Pane
This tab includes information about remaining duration, duration uncertainty, and risk notes.
Note: If you are working with cost uncertainty, then this tab is disabled.
Field | Description |
---|---|
Remaining | This field displays the remaining duration for the selected activity. |
Probability of Existence | If you are not 100% certain that a task is going to happen in your schedule, you can assign a probability to the task to reflect this confidence level. You can either enter a percentage in this field or in the % column on the S3 // Risk Activity grid. |
Enable Duration Uncertainty | Select this check box to enable duration uncertainty for the selected activity. When you select the check box, the following additional fields display:
Use the Minimum, Most Likely, and Maximum uncertainty fields to edit the percentage or duration for the selected activity. The values display both an absolute and a percentage value. If you change one, Acumen automatically recalculates the other. For example, if you change the percentage value, Acumen will automatically recalculate the absolute value as soon as you click off the field, and vice versa. |
Risk Notes | Use this text box to enter any additional notes about the activity risks. These notes are only available for reference on this tab and the Cost Uncertainty tab. |
Parent Topic: Activity Details Pane